Savoy Hotel Construction Update as of December 2015.

  • Installation of precast at 5th floor.
  • CHB laying and rubbed concrete works at Basement 1 to 3rd floor.
  • Waterproofing of retaining wall at Basement 1 &2.
  • Pipe sleeving and installation of stub out and other sanitary provision at Basement 2 to 6th floor.